Tuesday, June 8, 2010

Boeing restarts 787 part deliveries into Everett

As I had reported last week, Boeing will restart 787 final assembly on Monday, June 14th. This is reinforced with the restart of LCF flights bringing the required fuselage sections into Everett. Yesterday and LCF flew in the rear fuselage for the next 787 to be built...ZA177 (LN 23) for Japan Airlines and horizontal stabs for Air India's first 787, ZA230 (LN 25). Later this afternoon, the forward fuselage will be flown from Wichita to Everett. There should be a line move late this weekend to allow parts for the 23rd 787 to be located in the assembly tool in building 40-26.

Flight Test

ZA002 flew a 2 hour and 35 minute mission this morning (June 8th) out of Victorville. In completing this test flight, the 787 test fleet has completed over 30% of the required 3,100 test flight hours for the program. ZA005 continues its gauntlet testing ahead of a planned first flight on June 16th.